Parameter | Description | Content |
MV_QAPCTOL | Suggest a conditional approval report if there are measures out of the engineering limits, but within a specific tolerance. | S |
MV_QCALLIM | Enter if the control limits, greater and lower, will be fixed on the exhibition graph of the control letter. | F |
MV_QDIRGRA | Directory where the files (.SPC extension) used by the Control Chart graphics are created. | C:\ |
MV_QGINT | Enter if the Quality Protheus modules are integrated to the Personnel Management module, not enabled the option Add employees. | N |
MV_QIMPRCQ | Enter if the report printing Quality Certificate will be printed, without entering the General Report of inspection needs. N = do not print the Quality certificate without entering the General Report; S = print the Quality certificate without entering the General Report. | N |
MV_QINOBFM | When the instrument is not required and the test has linked families: 1 = Enable instrument 2 = Do not enable 3 = Enable Lab Report | 1 |
MV_QINVLTX | Enter if validates the instrument requirement for tests type Text. 1 = Yes 2 = No | 2 |
MV_QIPAVIS | Used to enter a warning message on measurement registration. | S |
MV_QIPFROT | Enter if should be used a primary operation route, of product specification, on Production Order opening. | T |
MV_QIPMAT | Enter if the Inspection Process module is integrated with Materials. | S |
MV_QIPMULT | Define the number of processes to be run by the routine, limited to 15 (fifteen) processes. This is because the greater the number of processes, the greater also the consumption processing. Example: 1= will be run one process, 2 = two processes, etc. | 1 |
MV_QIPOPEP | Define data priority in relation to the operation between the Process Inspection and Planning and Production Control modules, where: 1 - Production Control and Planning; 2 - Process Inspection. | 2 |
MV_QIPQMT | Integration between the Process Inspection and Metrology modules. | S |
MV_QIPQNC | Integration between the Process Inspection and Non-Conformity Control modules. | 1 |
MV_QLINS | Enter the instrument validation limit. | 3 |
MV_QPCAROT | Enter if the OP data Optimized Load will be run. Only the simplified layout. | 1 |
MV_QPCERPR | Certify the production with tests to inspect by skip-test evaluation. | N |
MV_QPCPROP | Load the first Operation on Results screen or make possible to the user to load the accepted operation. 1 = Yes 2 = No. Only the Simplified layout | 2 |
MV_QPDELG2 | Enter if, at deleting operations from the QIP module (table QQK) should also be automatically deleted the operations from the PCP module (table SG2). Options for this parameter: T=True, to delete tables in both modules; F=False, that maintain PCP operation deleted on QIP module. | F |
MV_QPIESMD | Define if IGNORE essays without measurements on Lab Report, even if they are Required 1 = Yes 2 = No | 2 |
MV_QPINAUT | Enter the automatic usage from the first measurement instrument(s). | S |
MV_QPINDIS | Enter the report that makes unavailable the Production Order. | E |
MV_QPINSOB | Enter if instrument specification is mandatory for results recording (SIGAQIP) | S |
MV_QPJUSLA | Reason for production order report certified by the skip-lot evaluation. | T |
MV_QPLDNIV | Define the level that the user should have, to issue lab reports, operation and general, respectively. The first position refer to the Lab Report, the second to the Operation Report, and the third and last to the General Report. The levels should be defined with value between 0 and 9. | 000 |
MV_QPLGAPR | When there is no Operation Report, the General Report should be: S (Approved), N (Rejected) or I (Equal to Lab Report) | S |
MV_QPLRAST | Enter if it will accept only the Totally Approved (T) or Partially Approved (P) report. | N |
MV_QPMEAUT | Enter the online results collection instrument usage. | N |
MV_QPNRSER | Enter if there is Production Order control and the product serial number. | F |
MV_QPOPINT | Define if the generated production orders for intermediary production by means of OP explosion routing will be inspected. Options: T=True, it indicates will be inspected; F=False, it indicates will not be inspected. | T |
MV_QPRESNC | Consider results that are not specified as non-conformities. | N |
MV_QPSKLPR | Enter the initial number of production for ski-lot application. | 3 |
MV_QPSKPTE | Enter if the skip test will be considered all productions or only for inspected productions. | 2 |
MV_QPSLFSO | Define if SUGEST OP Final Report even if there are Operations without Report. 1= Yes 2 = No | 2 |
MV_QPTRLAY | Enter which screen Results Inspection Layout will be presented to the user. 1 = Standard Layout 2 = Simplified Layout | 2 |
MV_QPVLIN | Enter if it will validate the instrument at the moment of the measurement. | S |
MV_QPVMDEL | Define if it will VALIDATE the deleted register for a required test in Report measurement. 1 = Yes 2 = No | 2 |
MV_QVLDTHR | Allow to retroact measurement dates. It can be set as: 1 – the system validates if the measurement date/time is greater or equal to the database system, greater or equal to the entry date to the lab and equal or greater than the Production Order date. 2 – the system consist if the measurement date is greater than Production Order Date. 3 – the system checks if the measurement date is greater or equal to system database and if it is greater or equal to Production Order date. | 1 |
MV_QVLENSR | Define if it will validate the measurement maintenance in Results, from the Process Inspection module: | T |